Glenora Road Station?

And what about Te Mahia and Westfield

 

I saw in the Auckland Transport Board Meeting closed agenda for this month as well as the forward program sheet that three stations are up for discussion and possible decisions.

They are:

  1. Whether to close Te Mahia and/or Westfield Stations
  2. Allow Glenora Road Station to be built next to the Takanini Village

 

The Agenda and Forward Program papers that caught my attention

 

 

Comments

I note that the discussion around all three stations is behind closed doors under the justification of frank and free discussion to which a decision will be noted (rather than actioned by the looks of it). All three stations have stirred up the emotions with Manurewa Local Board roping in the Mayor to get Te Mahia to stay open while Papakura Local Board and Councillor Calum Penrose are fighting to get Glenora Road Station built and operation (rather than Auckland Transport’s favoured Tironui Station).

What could be indicative around Westfield and Te Mahia is that they are on the Auckland Plan Transport Network funding program for upgrades. Meaning if full funding is available the stations would be upgraded within the next 10 years otherwise not at all under the current Basic Transport Network scenario. However, that APTN and BTN could change depending how the Governing Body treats the final version of the Long Term Plan next year.

That said Glenora Road Station is not on either the APTN or BTN but if Auckland Transport give it the green light then somehow the Council will need to get funding for it.

 

The agenda paper notes that the decisions around those three stations will be released in due course. It will be VERY interesting to see which way AT fall over these stations.

 

City Rail Link Start Date Set to 2018

Governing Body Agrees Finally

 

Just In:

After debating – well relitigating four years of previous debate the Governing Body in an extraordinary session of Council has agreed by a vote of 14-6 (one absent) for the main City Rail Link project to start 2018. That is Option Two of the recommendations per the agenda (below).

As for the Notice of Motions I called for well they didn’t happen (was to be expected but tried) so will try again in the Long Term Plan submission rounds early next year.

 

The debate itself which dragged from 1:30 to 4pm and should have realistically taken 45 minutes was absolute torture and shows the lack of capacity some of our elected representatives have in that Governing Body. The sole purpose of that debate today was to vote for Option Two and work out funding arrangements to satisfy the Auditor General’s concerns she has raised over the situation. NOT to push a personal barrow from the last four years and especially since the Government has agreed to the City Rail Link in the first place.

 

So yep again the Governing Body did screw up a debate and continue on its history path of being ineffectual as a collective. Which is a damned shame as we do have some fine and smart individual Councillors in there.

Bring on 2016!

 

Reference Post and link to agenda

Amendment to CRL Start Date in the Long Term Plan