Main Project Start Date was as predicted but still a win for Auckland As it was picked up in the presser yesterday the Mayor will be putting forward … Continue reading The Weekend Analysis: CRL 2018 Start Date Still a Win for Auckland
An issue causing hot discussion either here in the blog or in the wider community
Main Project Start Date was as predicted but still a win for Auckland As it was picked up in the presser yesterday the Mayor will be putting forward … Continue reading The Weekend Analysis: CRL 2018 Start Date Still a Win for Auckland
A more surprising presser hit our inbox(es) late this afternoon. It is on the City Rail Link and the start date for the main project (i.e not the enabling works).
From Auckland Council – specifically the Office of the Mayor:
Following discussions with Audit NZ, the Mayor is proposing an amendment in Council’s draft Long-term Plan 2015-2025 on the timing for construction of Auckland’s number one transport priority – the City Rail Link (CRL).
In its draft budget, Council has the CRL project commencing in 2015/16, based on an assumption government’s funding contribution for the project would also start next year, five years earlier than government has so far indicated.
On Tuesday 9 December, council will consider changing the assumption of timing of the government contribution to 2018/19. This will mean enablement works of $280 million will still take place in the first three years of the plan, but construction will not start until 2018/19. This will also delay the completion date to 2023.
Mayor Len Brown says:
“We have a track record of success with central government when it comes to the CRL – we have moved them from a position of total opposition to one of commitment for funding half the project from the year 2020,” says Mayor Len Brown.
“Yes, we still have to work with government on final timing, but I’m confident we can come to an agreement and get on and get this job done.
“I understand why Audit NZ feel that we need to take a more conservative approach to our financial projections and I am proposing that we develop the LTP based on a later timing of government contribution.”
Public consultation on the draft LTP begins January 23 next year. The final plan is due for adoption June 30, 2015.
—-ends—-
In the 2012-22 LTP we assumed central government funding would commence from the year 2015-16 and the financial data for the 2015-25 LTP has carried that assumption through. The consultation document has been written with three alternative scenarios set out for public consideration:
Scenario One
Financial information
| $ million Year ended 30 June |
Prior years | 2016 | 2017 | 2018 | 2019 | 2020 | 2021 | 2022 | 2023 | 2024 | 2025 | Total |
| Capital expenditure | 178 | 156 | 267 | 432 | 438 | 425 | 481 | 102 | -88 | 2,391 | ||
| Government contribution | 0 | 167 | 133 | 216 | 219 | 200 | 194 | 51 | -44 | 1,137 | ||
| CRL related closing debt | 163 | 155 | 295 | 528 | 778 | 1,047 | 1,318 | 1,343 | 1,271 | 1,243 | 1,215 |
Assumptions
Financial impacts
Scenario Two
Financial information
| $ million Year ended 30 June |
Prior years | 2016 | 2017 | 2018 | 2019 | 2020 | 2021 | 2022 | 2023 | 2024 | 2025 | Total |
| Capital expenditure | 178 | 145 | 177 | 78 | 319 | 372 | 416 | 464 | 201 | 137 | 2,488 | |
| Government contribution | 0 | 0 | 0 | 0 | 305 | 186 | 195 | 184 | 101 | 68 | 1,039 | |
| CRL related closing debt | 163 | 316 | 510 | 614 | 658 | 882 | 1,081 | 1,340 | 1,428 | 1,490 | 1,487 |
Assumptions
Financial impacts
……………
Again a simple explanation on how the City Rail Link works:
A Simple But Not Exhaustive Explanation of the City Rail Link
The City Rail Link and Auckland
As I explained to Rebekka’s dad the CRL works on the following premises:
As of current all Western Line trains run from Waitakere, Swanson and Henderson into Britomart on a trip that takes around an hour. Those trains must pass through Newmarket where there is a 3min stand down as drviers change ends to allow the Newmarket to Britomart leg of the trip.
The Western Line as a result mixes with the Southern Line and Onehunga Line trains causing congestion. To make matters worse those trains then get caught outside Britomart as they mix with Eastern Line Trains causing delays and congestion.The CRL would allow Western Line Trains from Mt Eden to travel down the 3.5km tunnel to Britomart skipping Newmarket and thus not running into Southern, Eastern and Onehunga Line Trains as a result. We also get two new stations on the CRL including Aotea which is going to be the busiest being in the middle of the CBD itself.Time savings go from 60mins to about 43mins there about from Swanson to Britomart via the CRL as a result. You will still get Swanson to Newmarket services that will then continue either on to Onehunga or even Papakura – the South to West services.As the Western Line services are removed from the Newmarket-Britomart leg this frees track space for Eastern, Southern and Onehunga Line trains allow their frequencies to go from 10mins to 5mins in the peak of peaks. This means a train from Papakura every 5mins in the peak if so needed. Result? Capacity increases and the allowances of new lines such as Airport and the North Shore (Botany would be serviced by a Sky Train concept).
That is how the CRL works – it services the bulk of Auckland….
………….
So a 2018 start date for the main project with the enabling works to start as soon as feasibly possible.
That date I have widely touted as a start date for the main project (2017-2018) since I wrote my Auckland Plan submission in 2011. The logic moving the main start date to 2018 in the agenda paper seems consistent in part to the reasoning I used for a 2018 start date for the main project.
It is good to see (although other questions on why so long to move the main start date to 2018 do come up) the Mayor seeking the amendment for the CRL start date via the 2015-2025 Long Term Plan. Now to get the true alternative funding sources that are not extra rates nor tolls sorted by 2018….
Next move falls to us the ratepayer and conversely the Government as well for their funding share…
I would say yes – at some levels Yes insofar at the main Council level, and that of the Council Control Organisations. Our Local Boards seem to or are … Continue reading Does Auckland Live in a Technocracy Rather Than A Democracy?
How it benefits Auckland I posted this in Facebook earlier this morning on how the City Rail Link benefits Auckland. It was in reaction to a Rant/Rave piece … Continue reading A Simple But Not Exhaustive Explanation of the City Rail Link
And so the Public Transport Users Association has put out their first project presser:
A group of local residents and would-be train users are meeting at the Huapai train station this Thursday, but they might be waiting a long time for a train. Despite proposed growth of thousands of new homes in Huapai and Riverhead, an existing railway line to the heart of the growth area, and existing stations and diesel rolling stock, Auckland Transport are not planning for trains.
A new group hopes to change that. The Public Transport Users Association is a voluntary organisation, newly established to give current and future public transport users a voice. They are launching their first campaign this week, to retain and extend rail services from Swanson to Waitakere and Huapai.
Chairperson of the new group, and former Chair of Auckland’s Regional Transport Committee, Christine Rose, who is a local bus and train user, says Waitakere and Kumeu communities must be the only communities in the region facing a worse public transport future, with the withdrawal of train services to Waitakere, and the cancellation of long-held plans for hourly rail services to Huapai.
“The Northwestern motorway is severely congested and can’t keep up with growth in our area. Auckland Transport have no plans for a decent, dedicated, congestion free bus way to the Northwest. But we do have a significant underutilised asset in the rail, stations and rolling stock, that could provide a viable alternative for existing and future commuters”.
The Public Transport Users Association is launching the WestRail campaign at 4 on 4 December, but have already been encouraged by locals in support of rail services to the area. Further engagement with the community will follow. The group are also engaging with locals at the Waitakere station from 7-9 on Thursday morning, talking to commuters and encouraging awareness about the feasibility and need for rail services retained and extended in our area.
Further Information
—-ends—-
Not the best project I can think of here with our limited funding towards Auckland Transport as is.
The problems:
Conclusion?
Not a good start for the PTUA……
A Walk Through on What Could Have Been In this podcast I give a walk through a Transit Orientated Development for Lot 59 Manukau. As I will cover tomorrow … Continue reading Walk Through: Manukau Interchange – An Alternative
Tomorrow for the last time this year the Auckland Development Committee meets in Town Hall. The agenda items cover:
Podcasts on a walk through of Manukau, plus why the Auckland Development Committee has attracted my ire will be going up today and tomorrow
How we can participate How the authorities choose to participate How does a public authority choose to participate and how would we like to participate: The IAP2 … Continue reading The Sunday BBQ – Public Participation
A prelude into why I don’t hold much confidence in this new CCO As mentioned on Thursday the Governing Body of Auckland Council resolved to send out to … Continue reading The Weekend Analysis: Grim Hopes For the new Development Auckland CCO
Sydney Shows What I have Told Auckland Council Needs to Be Done A Urban and Transport Infrastructure Led Development Yet again one of our more advanced cousins which in … Continue reading Sydney Leaves Auckland For Dead