Main Project Start Date was as predicted but still a win for Auckland As it was picked up in the presser yesterday the Mayor will be putting forward … Continue reading The Weekend Analysis: CRL 2018 Start Date Still a Win for Auckland
Main Project Start Date was as predicted but still a win for Auckland As it was picked up in the presser yesterday the Mayor will be putting forward … Continue reading The Weekend Analysis: CRL 2018 Start Date Still a Win for Auckland
A more surprising presser hit our inbox(es) late this afternoon. It is on the City Rail Link and the start date for the main project (i.e not the enabling works).
From Auckland Council – specifically the Office of the Mayor:
Following discussions with Audit NZ, the Mayor is proposing an amendment in Council’s draft Long-term Plan 2015-2025 on the timing for construction of Auckland’s number one transport priority – the City Rail Link (CRL).
In its draft budget, Council has the CRL project commencing in 2015/16, based on an assumption government’s funding contribution for the project would also start next year, five years earlier than government has so far indicated.
On Tuesday 9 December, council will consider changing the assumption of timing of the government contribution to 2018/19. This will mean enablement works of $280 million will still take place in the first three years of the plan, but construction will not start until 2018/19. This will also delay the completion date to 2023.
Mayor Len Brown says:
“We have a track record of success with central government when it comes to the CRL – we have moved them from a position of total opposition to one of commitment for funding half the project from the year 2020,” says Mayor Len Brown.
“Yes, we still have to work with government on final timing, but I’m confident we can come to an agreement and get on and get this job done.
“I understand why Audit NZ feel that we need to take a more conservative approach to our financial projections and I am proposing that we develop the LTP based on a later timing of government contribution.”
Public consultation on the draft LTP begins January 23 next year. The final plan is due for adoption June 30, 2015.
—-ends—-
In the 2012-22 LTP we assumed central government funding would commence from the year 2015-16 and the financial data for the 2015-25 LTP has carried that assumption through. The consultation document has been written with three alternative scenarios set out for public consideration:
Scenario One
Financial information
| $ million Year ended 30 June |
Prior years | 2016 | 2017 | 2018 | 2019 | 2020 | 2021 | 2022 | 2023 | 2024 | 2025 | Total |
| Capital expenditure | 178 | 156 | 267 | 432 | 438 | 425 | 481 | 102 | -88 | 2,391 | ||
| Government contribution | 0 | 167 | 133 | 216 | 219 | 200 | 194 | 51 | -44 | 1,137 | ||
| CRL related closing debt | 163 | 155 | 295 | 528 | 778 | 1,047 | 1,318 | 1,343 | 1,271 | 1,243 | 1,215 |
Assumptions
Financial impacts
Scenario Two
Financial information
| $ million Year ended 30 June |
Prior years | 2016 | 2017 | 2018 | 2019 | 2020 | 2021 | 2022 | 2023 | 2024 | 2025 | Total |
| Capital expenditure | 178 | 145 | 177 | 78 | 319 | 372 | 416 | 464 | 201 | 137 | 2,488 | |
| Government contribution | 0 | 0 | 0 | 0 | 305 | 186 | 195 | 184 | 101 | 68 | 1,039 | |
| CRL related closing debt | 163 | 316 | 510 | 614 | 658 | 882 | 1,081 | 1,340 | 1,428 | 1,490 | 1,487 |
Assumptions
Financial impacts
……………
Again a simple explanation on how the City Rail Link works:
A Simple But Not Exhaustive Explanation of the City Rail Link
The City Rail Link and Auckland
As I explained to Rebekka’s dad the CRL works on the following premises:
As of current all Western Line trains run from Waitakere, Swanson and Henderson into Britomart on a trip that takes around an hour. Those trains must pass through Newmarket where there is a 3min stand down as drviers change ends to allow the Newmarket to Britomart leg of the trip.
The Western Line as a result mixes with the Southern Line and Onehunga Line trains causing congestion. To make matters worse those trains then get caught outside Britomart as they mix with Eastern Line Trains causing delays and congestion.The CRL would allow Western Line Trains from Mt Eden to travel down the 3.5km tunnel to Britomart skipping Newmarket and thus not running into Southern, Eastern and Onehunga Line Trains as a result. We also get two new stations on the CRL including Aotea which is going to be the busiest being in the middle of the CBD itself.Time savings go from 60mins to about 43mins there about from Swanson to Britomart via the CRL as a result. You will still get Swanson to Newmarket services that will then continue either on to Onehunga or even Papakura – the South to West services.As the Western Line services are removed from the Newmarket-Britomart leg this frees track space for Eastern, Southern and Onehunga Line trains allow their frequencies to go from 10mins to 5mins in the peak of peaks. This means a train from Papakura every 5mins in the peak if so needed. Result? Capacity increases and the allowances of new lines such as Airport and the North Shore (Botany would be serviced by a Sky Train concept).
That is how the CRL works – it services the bulk of Auckland….
………….
So a 2018 start date for the main project with the enabling works to start as soon as feasibly possible.
That date I have widely touted as a start date for the main project (2017-2018) since I wrote my Auckland Plan submission in 2011. The logic moving the main start date to 2018 in the agenda paper seems consistent in part to the reasoning I used for a 2018 start date for the main project.
It is good to see (although other questions on why so long to move the main start date to 2018 do come up) the Mayor seeking the amendment for the CRL start date via the 2015-2025 Long Term Plan. Now to get the true alternative funding sources that are not extra rates nor tolls sorted by 2018….
Next move falls to us the ratepayer and conversely the Government as well for their funding share…
In reply to a claim From Auckland Council, and Quotable Value: No basis for ‘wildly wrong’ valuation claims – Council & QV Auckland Council and Quotable Value say … Continue reading Council And QV Replies to Claims About Auckland Valuations
Silo Mentality Drives People NUTS I was reading through the Auckland Development Committee agenda for next week and noted that the Otara-Papatoetoe Area Plan (which I put in a … Continue reading ARGH: Left Hand Not Talking To Right Hand AGAIN
And we are going to be consulted on: Yesterday the Governing Body resolved the Draft Long Term Plan 2015-2025 for consultation between late January and early March next … Continue reading What the Governing Body Resolved Yesterday
What we will be consulted on From Auckland Council: Decisions on transport referendum, development contributions and capping rates Auckland Council’s Governing Body today made a number of decisions related … Continue reading Resolutions Resolved At The Governing Body Over the 2015-2025 LTP
Auckland Council Governing Body to Deliberate on Transport Funding Referenda TODAY If people would listen to Radio NZ and read blogs more, the Herald article today on Council Officers opposing … Continue reading Referendum? What Referendum [Update]
Bi Partisanship against the Mayor We know Auckland Council officials are opposing while the Mayor has gone cold on a referendum on motorway tolls to help plug the $12 … Continue reading Councillors Unite For the Transport Referendum
Council Officials Say No Councillor Cathy Casey picked up this from Radio NZ late last night: $1.5m for motoring charges referendum Updated at 9:03 pm on 21 November … Continue reading Referendum on Motorway Tolls Goes Cold

At the moment, Auckland Transport are operating in a very uncertain funding environment as they deal with potentially lower LTP capital expenditure in the Basic Transport Network (BTN) versus that in the Auckland Plan Transport Network (APTN).
Auckland Transport have opted to progress design and potentially early works (within funding) on projects that would be funded in earlier years under the APTN to ensure momentum is not lost.
And in the case of these two projects, the following would be the desired timeline without the constrained BTN funding:
- Construction on the Manukau Bus Interchange project would start in the 1st quarter of 2015 with target completion in late 2015. Currently, the detailed design process is underway.
- Construction of the Otahuhu Bus Train Interchange would start later this month with expected completion in late 2015. Currently, the detailed design process is underway.
In addition, Auckland Transport are currently exploring re-prioritisation options for these 2 projects. As this is currently being worked through, no update to the draft LTP has been made. If re-prioritisation cannot be achieved in 2014/15 and in the early years of the LTP, Auckland Transport would only deliver on initial improvements within the current funding, with the delivery of full specification in 2020/21.
Current Basic Transport Network (the Mayors proposal) budgeted figures:
Manukau Bus Interchange
- We have design funding of $3.8m in 2014/15
- Then there is no funding provided in the BTN programme until 2020/21
- Total required funding is planned at $23.9m (inflated)
Otahuhu Bus Train Interchange
- We have design and some early works funding of $6.3m in 2014/15
- Then there is no funding provided in the BTN programme until 2020/21
- Total required funding is planned at $26.8m (inflated)
—-ends—–
Public Transport Projects Being Used as Political Weapons?
Updates as information comes to hand