Electric Trains Start on the Manukau Line – Monday [updated]

A delay but there

 

It seems Monday the 18th the Electric Trains will start running on the Manukau Line in the off-peak periods as part of that limited roll out. They were meant to start plying the Manukau Line on the 13th but that never happened.

 

September/October is when the Electric Train fleet should be fully replacing the diesels on the Manukau Line both peak and off-peak. Or will they?

 

With the Long Term Plan 2015-2025 budget cuts from Auckland Council delaying the purchase of more Electric Trains (beyond the 57 already on order) to beyond 2025 will we see our diesels still plying the network post 2015 when the Electrics are fully rolled out? Something yet to be seen as the LTP debates continue.

 

[Update from Auckland Transport]

A second rail line going electric

15/08/2014 04:18 p.m.

The roll-out of electric trains in Auckland steps up next week with the introduction of the new trains on the Manukau Line.

Initially electric trains will run on some off-peak services, they will be introduced to all services over the next month.

Auckland Transport’s Chief Operations Officer Greg Edmonds says the new trains have been very popular since their introduction on the Onehunga Line in April but with any transition we should be prepared for “teething problems.”

“We want to ensure our customers who use the trains to Manukau are getting a reliable service so we will be gradually increasing the number of electric trains over the next month.”

Meanwhile, testing continues across the rail network following an intermittent power fault which saw some Onehunga services affected. Mr Edmonds stresses there are no safety issues associated with the fault.

——-

Source: https://at.govt.nz/about-us/news-events/a-second-rail-line-going-electric/

 

 

Not Particularly “Thrilled” on the Onehunga Timetable Criticisms

Just leave it be, bed the EMU’s in, and roll it out when Manukau is on stream

 

And so we are at day 4 of the electric trains running on the Onehunga Line – our shortest line of the Auckland rail network. After a bit of a rocky start on Monday which was expected all seems to be bedding in well on the Onehunga Line and reviews of the EMU’s quite positive.

What was not positive was the fact that the timetable did not change (so an increase in frequencies) for the Onehunga Line to reflect the EMU’s on the line.

Knowing that a new timetable is due out (all fingers crossed) in October after the Manukau Line goes on stream with the EMU’s, and knowing what goes into timetable creations from my former life in Transdev I was not particularly amused at the criticisms levelled.

On the idea “ghosting” a timetable (so creating it well advance than implementing it at the set time) it can be done but would be best effective if all lines were done at once. Knowing the Southern Line has the freighters on it and at the risk of the freighter schedules changing (for whatever reason) I would be wondering if ghosting would have worked. If someone in the know could comment on this it would be greatly appreciated – thank you 🙂

 

Anyhow the current timetable is not flash but we are meant to be rolling to all EMU’s on all lines for weekend services at the end of the year. Although they are still wiring up the Western and Southern Lines at the moment so all EMU weekend services will be interesting if those two lines are not complete by then.

At the end of the day it is a game of patience especially as we are on the final stretch.

The new timetable comes out for all lines with better frequencies later in the year. We are bedding in new EMU’s so in my opinion the existing timetable suits it rather well.

Rather than “criticising” AT I give them and Transdev the tick of a job well done this week all things considering including the teething issues on Monday.

 

Now if Auckland Transport can claw back those roll out dates for the Southern and Western Lines next year I guarantee some very happy people including me.

Our EMU’s are here and South Auckland gets the new bus network first up next year. Along with integrated fares I can say I have a 🙂 on my face for where we have got to so far. That said I also know the road ahead and I mentioned here: “Now We are Electrified, What Next?

 

As for when I will catch my first EMU? Most likely later in the year when they ply the Manukau Line 🙂

Night Closures on Rail Line to be Extended

Southern, Eastern and Manukau Lines to be Closed from 8:30pm 7-Days a week

 

I had received some feedback in regards to the Auckland Electrification Project – specifically around delays and setbacks. I sent some questions to Auckland Transport who have replied this morning in regards to the Electrification roll out (the infrastructure not the EMU trains).

 

While I will need to follow-up with Kiwi Rail in regards to Electrification completion on the Eastern Line (from Westfield Junction to Britomart), Newmarket to Britomart and Britomart Station itself I do have confirmation of extended closures on the rail line south of Otahuhu Station starting this coming Friday.

 

As Southern Auckland rail commuters are aware, from May 27 this year the rail line between Otahuhu and Papakura (including the Manukau Line and Station) would close at 8:30pm – Sunday to Thursday. That means the 8:10pm Britomart to Papakura va Newmarket service is the last full service through to Papakura. After 8:30pm your train will go as far on the Eastern, Southern and Manukau Lines to Otahuhu where you will need to transfer to a Rail Bus to finish your journey. The closure is to allow continued work on the Electrification project in the area.

 

However this “ramp down” as we call it in the rail transport trade is now to occur seven days a week until the Christmas-New Year Close Down Auckland is use too for the last several years. That means: the 8:10pm Britomart to Papakura va Newmarket service is the last full service through to Papakura. After 8:30pm your train will go as far on the Eastern, Southern and Manukau Lines to Otahuhu where you will need to transfer to a Rail Bus to finish your journey – SEVEN DAYS A WEEK starting this week.

 

Please direct your enquiries on the “ramp down” of services to Auckland Transport please – not Talking Auckland

 

 

So again 

From this coming Friday 11th October 2013 until the Christmas/New Close Down, from 8:30pm – seven days a week (unless otherwise stated by Auckland Transport such as a Special Event); Southern, Eastern and Manukau Line Trains will only run between Britomart and Otahuhu. To go further south (or to come north  from south of Otahuhu) you will need to complete/start your journey on a rail bus. Western and Onehunga Line not affected by this ramp down.